Installation of Utilities

ARTICLE F. INSTALLATION OF UTILITIES.

  • 1. Location. Connection. and Backfilling. All utility lines and other subsurface facilities within street rights-of-way shall be installed between the curb lines of the street rights-of-way. The lot connections of said facilities shall extend to the property lines. The backfill shall be allowed to settle for a minimum of 30 (thirty) days prior to the preparation of the street sub- base, unless the Municipal Engineer determines a longer time is required.

  • 2. Water Mains. Installation of water mains shall be in conformance to the "American Water Works Association Standard Specifications for Residential Subdivisions", and such other specifications as may be required by the water district providing the service.